| 1 | PT. Pijar Utama | JKA 42 Pijar | 106,57 Ton | Jombang - Madiun | Railway Bridge | January | OFF |
| 2 | Samsung C & T Corporation | Pile Binder | 0,45 Ton | Karawang | Power Plan | February | OFF |
| 3 | Samsung C & T Corporation | H-Beam Platform For Cep Casing Installation | 2,70 Ton | Karawang | Power Plan | March | OFF |
| 4 | Samsung C & T Corporation | Indonesia Jawa I CCP | 4.661 Ton | Karawang | Power Plan | April | OFF |
| 5 | Samsung C & T Corporation | Shim Plate | - | Karawang | Power Plan | May | OFF |
| 6 | PT. Karya Mitra Jaya Perkasa | Jembatan Rangka Baja Tipe A80 Lae Renun | 366,48 Ton | Medan | Steel Girder Bridge | May | OFF |
| 7 | PT. Mitra Aiyangga Nusantara | Jembatan Rangka Baja Tipe A80 Kalaena | 382,13 Ton | Makasar | Steel Girder Bridge | May | OFF |
| 8 | PT. Putragaya Wahana | Outrigger & Belt Truss Tower 2 PGW | 1.449 Ton | Jakarta | | May | OFF |
| 9 | Agung - Maju Wira KSO | JKA 60 +26,5+15,6 Agung - Maju | 275,52 Ton | Palembang | Railway Bridge | June | OFF |
| 10 | BUT Sumitomo Corporation | Support For Cable Tray | 1 Set | Jepara | | July | OFF |
| 11 | Shimizu BCK | Supply of Pipe Column Mock Up | 2,31 Ton | Jakarta | | July | OFF |
| 12 | PT. Duta Pratama Indah | JKA CHS 16,8 Duta Pratama Indah | 20,42 Ton | Kroya - Jogja | Railway Bridge | July | OFF |
| 13 | PT. Karyabaru Adyapratama | JKA CHS 26 Karyabaru | 44,79 Ton | Kroya - Jogja | Railway Bridge | August | OFF |
| 14 | Sumitomo Corporation | Pipe Support Beam Sumitomo | - | Jepara | | August | OFF |
| 15 | PT. Jaya Teka Prima | JKA 15,86 Jaya Teka | 32,40 Ton | Padang | Railway Bridge | August | OFF |
| 16 | Samsung C & T Corporation | HRSG Base Plate Samsung | 1.15 Ton | Karawang | Power Plan | August | OFF |
| 17 | PT. Selosari | JKA 46,5X2 Selosari | 221 Ton | Mojokerto - Jombang | Railway Bridge | August | OFF |
| 18 | Black & Veatch | Blasting & Painting | | Tangerang | | September | OFF |
| 19 | PT. Usaha Multi Guna | JKA B8,8 Usaha Multi Guna | 6,94 Ton | Kroya - Jogja | Railway Bridge | September | OFF |
| 20 | PT. Matlamat Cakera Canggih | Spilce Plate Cirebon - 2 CFPP | 0,74 Ton | Cirebon | | September | OFF |
| 21 | PT. Cipta Mukti Utama | Baut JKA S10T Cipta Mukti Utama | 1.081 pcs | Solo - Wonogiri | Railway Bridge | September | OFF |
| 22 | PT. Ergates Citra Mandiri | JKA B10 Ergates Citra Mandiri | 11,31 Ton | Mojokerto - Jombang | Railway Bridge | September | OFF |
| 23 | PT. Bhinneka Cipta Yasa | JKA WTP 15,56+B10,8 Bhinneka | 37,55 Ton | Mojokerto - Jombang | Railway Bridge | September | OFF |
| 24 | PT. Krida Utama | JKA WTP21 Krida Utama | 42,08 Ton | Mojokerto - Jombang | Railway Bridge | September | OFF |
| 25 | PT. Mitsui Indonesia | Loading & Unloading Material | 1.000 Ton | Cirebon | | September | OFF |
| 26 | PT. Ganda Karya Utama | JKA WTP26,55+B7,2 Ganda Karya Utama | 70,20 Ton | Mojokerto - Jombang | Railway Bridge | September | OFF |
| 27 | PT. Prawiramas Puriprima | JKA WTP32 Prawiramas Puriprima | 84,56 Ton | Mojokerto - Jombang | Railway Bridge | September | OFF |
| 28 | PT. Murinda Iron Steel | Fabrikasi Cutting & Drilling Murinda | 500 Ton | Jakarta | | September | OFF |
| 29 | Mitsubishi Corporation | Platform Dearator & General Access | 1 Unit | Sulawesi Selatan | | October | OFF |
| 30 | PT. karya Putra Yasa | Platform Jembatan KA BH 1769 | 3,56 Ton | Jawa Tengah | | November | OFF |
| 31 | PT. Budi Bakti Prima | JRA A60 & A25X2 Budi Bakti Prima | 393,45 Ton | Lahat - Sumsel | | November | OFF |
| 32 | PT. Total Bangun P. - Berca Buana S. JO | Structur Baja Atap Skylight LT 5 & Ice Word | 673,79 Ton | Jakarta | Steel Structur | November | OFF |
| 33 | Sumitomo Corporation | ADD. Repair Column Tanjung Jati B | 6,33 Ton | Jepara | | December | OFF |
| 34 | PT. Vin Septa Jaya | JKA WTT42 Vin Septa Jaya | 106,57 Ton | Bogor | Railway Bridge | December | OFF |